Installation is finished, the press is level, and the order is waiting. Between commissioning and the start of production there is a short list of checks worth doing in writing, because each one is cheap now and expensive later.
Foundation and anchoring. Confirm the foundation matches the drawing, that anchor bolts are torqued to spec and that levelling has not drifted since grouting. For impact machines, a damping foundation isolates the shock from the building and from neighbouring equipment; check that the gap and the resilient elements are as designed. Re-check level after a week of running, when settlement shows up.
Safety functions. Simulate a power loss and an air failure and confirm that emergency braking and the stopping sequence behave as specified. Test the two-hand control, the light curtain or the safety gate, and the slide locking device used during die changes. These are the checks a pre-delivery test repeats at the factory; they should be repeated on site, in the real installation.
Strike force. Set the tonnage for the actual die and verify it with a tonnage tester or a calibrated load cell, at more than one setting. A press that cannot repeat the same energy at three different settings cannot hold a process window, whatever the nameplate says.
Speed and stroke setting. Run the slide at the high and low ends of the programmed range and confirm the transition is stable. Multi-blow sequences for venting and finishing depend on this.
Full cycle run. Run the complete cycle, loaded, for a few hours: feeding, forming, ejection, handling. Watch for abnormal noise, temperature rise in the screw assembly and drift in the bottom dead position.
Handover documents. Collect the parameter sheet, the electrical drawings, the lubrication chart and the alarm list before the crew starts. Sign off the training on die change and on recovering from a fault. A press that nobody can re-set after a die change is not commissioned.
Initial part. Measure the parts from the initial run against the drawing under GB/T 12362 tolerances, then repeat after 50 and 200 strokes. If the spread stays inside the window, the press and the process are ready. If it widens, stop and find the cause before the shift starts.